BabyLove Schedule
August 1- Aug 28 - complete ALL ID design and development (hardware+software)
Aug 29 - - send in for teacup FRP + baby mold
Aug 29- Oct 9 (6 weeks) - teacup and baby FRP mold making
Sept 19 - Sept 25 - Sony computer lab programming session (shulea+atau+ali)
Oct 10 - complete mold
October 10- October 23 (2 weeks) - Shulea in taipei - review teacup mold and hard+soft-installation
Oct 10- Oct 24 (2 weeks) - teacup(7) and baby(7) production
Oct 24 - complete ALL fabrication (teacup and baby)
Oct 24- Nov 10 (3 weeks) - hardware+software- integration (taiwan) with Paris (remote) - Shulea in Paris (remote with taiwan)
Oct 24 - Nov 7 crate fabrication
nov 11- nov 14 (3 days) - crated and load for shipping (air cargo)
Nov 14- nov 24 - air cargo/customs
nov 25- dec 6 - gallery installation/testing (paris)
Dec 7, vernissage
Dec 8, 2005 - Jan 8 (one month) , 2005 exhibition palais de Tokyo
Aug 29 - - send in for teacup FRP + baby mold
Aug 29- Oct 9 (6 weeks) - teacup and baby FRP mold making
Sept 19 - Sept 25 - Sony computer lab programming session (shulea+atau+ali)
Oct 10 - complete mold
October 10- October 23 (2 weeks) - Shulea in taipei - review teacup mold and hard+soft-installation
Oct 10- Oct 24 (2 weeks) - teacup(7) and baby(7) production
Oct 24 - complete ALL fabrication (teacup and baby)
Oct 24- Nov 10 (3 weeks) - hardware+software- integration (taiwan) with Paris (remote) - Shulea in Paris (remote with taiwan)
Oct 24 - Nov 7 crate fabrication
nov 11- nov 14 (3 days) - crated and load for shipping (air cargo)
Nov 14- nov 24 - air cargo/customs
nov 25- dec 6 - gallery installation/testing (paris)
Dec 7, vernissage
Dec 8, 2005 - Jan 8 (one month) , 2005 exhibition palais de Tokyo